ArchicadReleaseannounced 2026 product portfolio with AI design capabilitiesv202636dALLPLANReleasepublished 2026 release notesv2026105dTekla StructuresReleasereleased Tekla 2026 with AI model and drawing assistant previewv2026246dThat Open EngineIFC capabilityadded partial IFC4.3 alignment supportv3.1.245dAutodesk FormaUpdateadded embodied carbon analysis for massingv2026.0946dAutodesk Construction CloudReleasereleased September platform updatev2026.0947dTrimble ConnectIFC capabilityadded IDS validation (beta)v2026.0949dFinchUpdateupdated Grasshopper connectorv2026.949dSpeckleReleasereleased version 3.4v3.450dAugmentaNew listingadded to the indexv1.451dIFC Validation ServiceIFC capabilityexpanded IFC4.3 normative rulesv2026.951dBonsaiReleasereleased version 0.8.3v0.8.352dIfcOpenShellReleasereleased version 0.8.3v0.8.352dCatenda HubNew listingadded to the indexv2026.953dAutodesk TandemPricing changechanged pricing tiersv2026.0953dSolibri OfficeReleasereleased version 25.9v25.955dVerasUpdateupdated AI render enginev2.655dSwappNew listingadded to the indexv2026.855dRhinoReleasereleased 8 SR24v8 SR2457dRevitReleasereleased version 2027.1v2027.158dxeokit SDKNew listingadded to the indexv2.759dProSheetsUpdateplugin updated for Revit 2027v2.460dIdeate BIMLinkNew listingadded to the indexv2027.162dArchicadReleasereleased version 29.1v29.163dusBIM.viewer+New listingadded to the indexv202665dEnscapeReleasereleased version 4.12v4.1265dThat Open EngineNew listingadded to the indexv3.168dpyRevitReleasereleased version 5.1v5.172dArchicadReleasereleased version 29v29141dBonsaiReleasereleased version 0.8.2v0.8.2163dRevitReleasereleased version 2027v2027218dArchicadReleaseannounced 2026 product portfolio with AI design capabilitiesv202636dALLPLANReleasepublished 2026 release notesv2026105dTekla StructuresReleasereleased Tekla 2026 with AI model and drawing assistant previewv2026246dThat Open EngineIFC capabilityadded partial IFC4.3 alignment supportv3.1.245dAutodesk FormaUpdateadded embodied carbon analysis for massingv2026.0946dAutodesk Construction CloudReleasereleased September platform updatev2026.0947dTrimble ConnectIFC capabilityadded IDS validation (beta)v2026.0949dFinchUpdateupdated Grasshopper connectorv2026.949dSpeckleReleasereleased version 3.4v3.450dAugmentaNew listingadded to the indexv1.451dIFC Validation ServiceIFC capabilityexpanded IFC4.3 normative rulesv2026.951dBonsaiReleasereleased version 0.8.3v0.8.352dIfcOpenShellReleasereleased version 0.8.3v0.8.352dCatenda HubNew listingadded to the indexv2026.953dAutodesk TandemPricing changechanged pricing tiersv2026.0953dSolibri OfficeReleasereleased version 25.9v25.955dVerasUpdateupdated AI render enginev2.655dSwappNew listingadded to the indexv2026.855dRhinoReleasereleased 8 SR24v8 SR2457dRevitReleasereleased version 2027.1v2027.158dxeokit SDKNew listingadded to the indexv2.759dProSheetsUpdateplugin updated for Revit 2027v2.460dIdeate BIMLinkNew listingadded to the indexv2027.162dArchicadReleasereleased version 29.1v29.163dusBIM.viewer+New listingadded to the indexv202665dEnscapeReleasereleased version 4.12v4.1265dThat Open EngineNew listingadded to the indexv3.168dpyRevitReleasereleased version 5.1v5.172dArchicadReleasereleased version 29v29141dBonsaiReleasereleased version 0.8.2v0.8.2163dRevitReleasereleased version 2027v2027218d
GuideBIM fundamentals

What is BIM? A complete guide to Building Information Modeling

BIM is the process of creating and managing structured digital information about a built asset across its whole life. This guide explains what that means in practice, how BIM differs from CAD, which standards hold it together, and how to choose tools that actually exchange information.

Updated 8 November 202615 min readSources cited
Key takeaways
  • BIM is a process for managing structured asset information, not a 3D rendering exercise.
  • Models are useful because they can be queried: quantities, checks, asset data and handover.
  • IFC, BCF, IDS and ISO 19650 are what make information portable between organisations.
  • Software is chosen for interoperability and data behaviour, not feature-count marketing.
Jump to a section
  1. What BIM is
  2. How BIM works
  3. BIM vs CAD
  4. Standards and open formats
  5. Benefits
  6. Where BIM is used
  7. Roles and deliverables
  8. The software landscape
  9. Getting started
  10. Frequently asked questions
  11. Sources
01

What BIM actually is

Building Information Modeling (BIM) is the process of creating, sharing and managing structured digital information about a built asset across its life cycle. The information is held in a model made of objects that represent real building elements, each carrying attributes such as type, material, dimensions, cost and maintenance requirements.

“Use of a shared digital representation of a built asset to facilitate design, construction and operation processes to form a reliable basis for decisions.”
ISO 19650-1, concepts and principles

The acronym is used in three related ways. It is the process of producing and managing information, the model that holds it, and the management of that information between organisations. That third meaning matters: most BIM failures are information failures, not modelling failures.

The practical test of whether something is BIM is not how good it looks on screen. It is whether you can query it. Can you count every door with a specific fire rating, check a level against a clash, price a change, or hand an asset register to a facilities team? If yes, you are working in BIM regardless of which tool produced the model.

02

How BIM works in practice

A BIM process links who needs what information, when, and in which format. On a typical project the loop runs like this:

  1. 1Define requirements. The client states what it needs the asset to do and what information it needs to manage it. On ISO 19650 projects this appears as exchange information requirements (EIR) for delivery and asset information requirements (AIR) for operation.
  2. 2Plan the delivery. The delivery team responds with a BIM execution plan (BEP), a master information delivery plan (MIDP) and task information delivery plans (TIDP) that name the models, owners and dates.
  3. 3Author discipline models. Architecture, structure, MEP and civil teams model their scope at the agreed level of information need, in tools suited to their discipline.
  4. 4Federate and coordinate. Discipline models are combined for spatial coordination and clash detection. Issues are raised, assigned and tracked, usually in BCF so the conversation stays attached to the element.
  5. 5Check against requirements. Automated checking validates the model against the client requirements: classifications, data completeness, and rules such as clearances or fire ratings.
  6. 6Share through a CDE. Models and documents move through a common data environment with controlled states, so published information is always the current, approved version.
  7. 7Hand over and operate. At completion the information is issued as an asset information model: COBie data, as-built models, O&M documentation, and the basis for digital twin or facility management systems.

On top of geometry, teams add time, cost and performance: 4D links model objects to a construction programme, 5D attaches quantities and cost, and 6D covers performance and sustainability data. These are views on the same information, not separate models, and they only work if the underlying data is consistent.

03

BIM vs CAD: the difference that matters

CAD (computer-aided design) is a drafting technology. BIM is an information technology that also produces drawings. Both can describe the same building, but they behave very differently when the design changes or another team needs the data.

CADBIM
Primary artefactA set of drawings: plans, sections, detailsAn object-based model plus the information attached to it
GeometryLines, arcs and annotations representing a designBuilding elements with type, material, dimensions and relationships
ChangeEach drawing is edited and reissued separatelyEdit once, and views, schedules and quantities update together
CoordinationOverlay drawings and compare manuallyFederate models and detect clashes and data conflicts
Data reuseMostly visual, limited extractable dataQuantities, specifications, asset registers and handover data
In operationAs-built drawings are archivedThe model and its data can feed maintenance and asset management

In practice the two coexist. Detail drawings, reinforcement bar lists and survey data still use drafting conventions, and many practices run hybrid workflows. The distinction that matters for selection is whether a tool authors information models or only documents them.

04

Standards, open formats and interoperability

BIM only pays off when information can move between organisations and tools. That is why the standards ecosystem matters more than any single software licence.

ISO 19650
Information management over the asset life cycle: concepts, delivery phase and operational phase. Defines information requirements, the CDE and the exchange process.
IFC
The open BIM data format, standardised as ISO 16739. Transfers geometry and data between tools, with model view definitions narrowing what must be exchanged for a specific use.
IDS
Information Delivery Specification: a machine-readable way to state the information a model must contain, so compliance can be checked automatically rather than argued over.
BCF
BIM Collaboration Format: carries issues, viewpoints and comments between coordination tools and authoring software, so a markup stays linked to the element it refers to.
bSDD
buildingSMART Data Dictionary: a shared classification and property source, so “fire rating” means the same thing in every model.
COBie
A structured handover dataset for asset information, commonly required at practical completion and read by facilities management systems.

Public-sector mandates vary by country and continue to evolve, so the requirement that matters is the one written into your appointment or contract. Rather than assume a tool is compliant, check documented support for the exact IFC version, IDS rules and BCF exchange your project specifies. Our OpenBIM hub tracks IFC 2x3, IFC4, IFC4.3, BCF, IDS and bSDD support per product, with the source for each claim.

05

What BIM is actually good for

  • Better decisions earlier. Options can be modelled, measured and compared before commitments are made, when change is cheapest.
  • Fewer coordination surprises. Federated models surface clashes and clearance problems in the office rather than on site.
  • Reliable quantities and cost. Consistent object data supports take-offs, 5D cost models and change pricing without re-measuring drawings.
  • Constructability and programme. 4D sequencing tests the build order, temporary works and site logistics before mobilisation.
  • Manufacturing accuracy. Detailing models drive fabrication and prefabrication, where tolerance errors are expensive.
  • Carbon and performance analysis. Material quantities feed embodied carbon and energy studies directly from the model.
  • A usable handover. Asset data, O&M information and as-built models reduce the effort of commissioning and operation.
  • Safer projects. Clash-free, sequenced models reduce rework, hot works conflicts and unplanned work at height.

These benefits are conditional. Evidence from industry surveys, including the NBS Digital Construction Report, consistently shows that value depends on clear requirements, trained teams and information being used rather than merely produced.

06

Where BIM is used

BIM is applied wherever an asset is complex enough that coordination and information continuity outweigh the cost of modelling.

  • Buildings. Architectural, structural and MEP coordination, compliance checking, and fit-out with asset data for operation.
  • Infrastructure. Roads, rail, bridges and utilities modelled with alignment-based tools, then federated with structures and systems. See the global infrastructure map for software in verified use on major programmes.
  • Energy and industrial. Plant, piping and equipment models where clash avoidance and as-built accuracy drive shutdown planning. Hinkley Point C is a documented example.
  • Existing assets. Survey and scan-to-BIM workflows capture what is already built, for refurbishment, adaptation or a digital twin.
  • Operation. Asset information models feed maintenance planning, space management and connected building systems.
07

Roles, appointments and deliverables

BIM changes who is accountable for information, not just how drawings are produced. The roles below appear in most formal frameworks; titles differ between organisations, so check the definition in the appointment rather than the job advert.

Information manager
Sets up and runs the information management process: requirements, the CDE, exchange schedules and compliance with ISO 19650.
BIM manager
Owns standards, templates, content and capability inside an organisation, and often represents it in project setup.
BIM coordinator
Runs day-to-day federation, clash resolution and model quality across disciplines.
Discipline leads
Author and QA their own models, and own the data their scope delivers.
Client or asset owner
Defines the information requirements and receives the asset information model at handover.

The documents that make it work are unglamorous and decisive: exchange information requirements, a BIM execution plan, MIDP and TIDPs, a federation schedule, and a naming and classification convention everyone actually follows.

08

The BIM software landscape

No single product covers a project. A working stack spans authoring, coordination, checking, a common data environment and analysis, chosen so that information survives the handoffs between them.

Authoring

Architectural, structural, MEP and civil design tools that create the models.

Coordination and review

Federated model review, clash detection, issue tracking with BCF.

Checking and compliance

Rule-based model checking against requirements and building codes.

Common data environment

Controlled information sharing, versioning and approval across the team.

4D and 5D

Programme simulation and cost-linked quantities.

Analysis

Structural, energy and carbon tools that read model data directly.

Field and handover

Site access to models, snagging, commissioning and asset data.

Open source and APIs

Scripted, automatable workflows and IFC libraries for custom pipelines.

Start with the full software market to filter by IFC version, API support, deployment and security posture, then shortlist with the side-by-side comparison.

Be sceptical of “BIM capable” as a marketing term. Ask which IFC version the tool imports and exports, whether it maps custom property sets, what it does with classifications, and whether issue exchange is BCF-based. BMI records each of these with a provenance label so you can see whether a claim is verified, vendor reported or community reported.

09

Getting started without wasting a year

  1. 1Pick one real project and one clear use case: coordination, quantity take-off or compliance checking. Do not attempt a firm-wide transformation first.
  2. 2Write down what information you need and who needs it, before choosing software.
  3. 3Agree the exchange format and version (IFC 4 or IFC 4.3), plus how issues will be exchanged (BCF).
  4. 4Set up a single location for current, approved information, even if it is a shared folder with strict discipline.
  5. 5Train one coordinator properly. Skills, not licences, are usually the constraint.
  6. 6Measure something: clashes resolved before site, hours saved on take-off, change orders avoided.
  7. 7Expand to other disciplines only once the first loop works end to end.

If you are choosing tooling, start from requirements rather than brand: the selection assessment scores the market against interoperability, security and commercial criteria you set.

10

Frequently asked questions

What does BIM stand for?

BIM stands for Building Information Modeling: the process of creating, sharing and managing structured digital information about a built asset. The term is also used for the information model itself (a Building Information Model) and, in ISO 19650, for building information modelling and management across the whole life cycle of an asset.

Is BIM just 3D modelling?

No. Geometry is only one part of a BIM model. The value comes from the information attached to each object (type, material, fire rating, cost, maintenance schedule, manufacturer) and the relationships between objects, so the same model can drive drawings, schedules, quantities, coordination checks and asset handover.

What is the difference between BIM and CAD?

CAD produces drawings, typically lines, arcs and text that describe a design. BIM produces objects that represent real building elements and carry data, so plans, sections and schedules are generated from the model and stay consistent when the design changes.

What is IFC and why does it matter?

IFC (Industry Foundation Classes) is the open, vendor-neutral data format for BIM, published by buildingSMART and standardised as ISO 16739. It lets models and data move between different authoring, analysis and coordination tools without a proprietary export of the whole project.

What is ISO 19650?

ISO 19650 is the international standard for managing information over the life cycle of a built asset using BIM. Part 1 covers concepts and principles, Part 2 covers the delivery phase and Part 3 covers the operational phase. It grew out of the UK PAS 1192 series and is now the common reference for information requirements, exchange and the common data environment.

What is a common data environment (CDE)?

A common data environment is the agreed single source of information for a project, used to collect, manage and share models, documents and other deliverables. Under ISO 19650 a CDE has controlled states (work in progress, shared, published, archived) so that everyone works from the same, current information.

What do LOD and level of information need mean?

Level of detail or development (LOD) is a shorthand for how developed a model element is at a given stage. EN 17412-1 replaces that shorthand with level of information need: the purpose, the information deliverables and the level of granularity agreed for a specific use, so teams specify what is actually required rather than a single number.

Do I need BIM software to work with BIM?

Authoring, coordination and checking tools do the heavy lifting, but BIM information is also read in free viewers, open-source libraries and web platforms. What matters is that the tools you choose exchange IFC, BCF and documents reliably with the rest of the project team.

Is BIM only for buildings?

No. The same principles apply to roads, rail, bridges, energy and water infrastructure. Infrastructure projects often combine civil design, structural detailing and federated coordination in one information management framework, as the examples on our infrastructure map show.

Still deciding how BIM fits your workflow?Ask the communitySuggest a correction
11

Sources

Standards and industry guidance referenced above. Where a claim concerns a specific product, the source is recorded on that product’s BMI page.

Last reviewed 2026-11-08.